Mendota HS HVAC Replacement - RE-BID

Status

Bidding Closed

Prebid Date 9/22/23 2:00pm
Bid Date 10/10/23 2:00pm

Company & Contacts

PBK
Rafael Ferreira  
559.448.8400

Re-Bid for the Mendota HS HVAC project

Additional Instructions

Re-Bid project. The district has determined that the work scheduled for Buildings 500 (MPR) and Building 700 (Gymnasium) scope of work shall be performed during summer months (May, June and July 2024) or once the HVAC and Electrical equipment is available. No temporary partitions or functional HVAC system shall be required for Buildings 500 and 700. A Non-Mandatory pre-bid conference will be held on September 22, 2023, at 2:00PM. (PDT). The group will tour the site at 2:00 PM. Meet at the Mendota High School Administration Building at 2:00 PM.